Building Project Pictures September
and October 2002
In
early September some shrubs at the right front of the Church
were removed and stored, to be replaced later.
On September 23rd stakes were placed marking areas of excavation.
On
September 24th some trees were cut. Many were diseased. On September
26th a front-end loader pushed sod and topsoil to an area adjacent
to the church. It will be pushed back in place when the building
is complete.
Fr.
George is holding the Permit sign in front of Jance General
Building Contractors construction trailer.
On October
3rd the Stained Glass window at the Baptistery is covered
to protect it during construction from the inside of the Church.
On
October 3rd the Large window on the site side of the church
is covered for protection.
On
Sunday October 6th a simple Celebration and Blessing of the
ground was held at the church for all parishioners.
Refreshments
and balloons were available for everyone!
The refreshments
included brick cheese, dirt cake, and stained glass cookies!
Alice reads
from scripture.
Fr.
George leads prayer and blessing.
A beautiful
Fall day!
Oct
6th 2002
October
7th through 11th:
New electric line was laid. A large green box -- the electric
connection box -- stood tall on the site hill.
The interior temporary walls were painted white.
Some of
the exterior stone, where expansion will occur was removed and
set aside; to be replaced upon building completion.
October
16th:
All electric and gas lines installed. Electric lines are 39
inches deep and gas 18 to 20 inches deep. They go back to the
addition of the new chapel.
Able Fence installed fencing surrounding the entire site.
All inside added "protection" walls painted white.
A tool storage area was placed in the Narthex and also painted
white.
October
22nd:
It is anticipated the project will take 7 months. We will be
out of the Church in January and February. Services will take
place in the Large Hall.
Concerning
the Nursery: families were surveyed and the majority preferred
to have the nursery adjacent to preschool in the lower level
of the new wing.
There is
a proposal before the Willoughby Hills Building Inspector that
would allow us an additional 18 parking spaces on the side of
the new wing. The soil from excavation will be used as a base
for this parking area.
October
23rd:
The area where the Chapel will stand needed adjustment. More
clay was added for a firmer foundation. A cement slab is to
be poured over the area prior to Chapel construction.
Earth moving
equipment dug and moved soil aside, making way for the basement
areas for the new wing. As the work progressed some additional
problems developed -- pylons set under ground at the time of
original building needed to be removed.
Also parts
of the original foundations need reinforcement. The basement
area will continue to be readied before construction can begin.
October
30th
Footers were set and below ground walls supported and reinforced
where necessary.
Large gravel was laid as a roadway for the large equipment.
Please
come back here weekly for updates to our
"Foundation for the Future" building project!
If you have
questions concerning any information contained on the Saint Noel
Parish Web site, contact us. Our staff
will answer your questions or forward you to the appropriate individual
or group.